The following is an example of implementation schedule for an ERP finance system. Total period requires 2 months at least :
| SN | Phase / Task | Owner | Department Involved | Start Date | End Date | Est.Day | Status | Actual Date | |
| PREPARATION | |||||||||
| 0 | Project Initiation | ||||||||
| 0.10 | Select Project Manager | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
| 0.20 | Prepare Project Kick-off Meeting | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
| 0.30 | Develop preliminary project scope and schedule | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
| 1 | Kick Off Meeting | ||||||||
| 1.1 | Project Team Member List Arrangement | Both | Project Team | 7-Nov-11 | 11-Nov-11 | 0.50 | |||
| 1.2 | Prelimilary Understanding the Company Background, structure and others of Company | Kingdee | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
| 1.3 | Present the implementation workflow, ways and contents | Kingdee | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
| 1.4 | Define the implementation schedule | Both | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
| 1.5 | Deliver the Masterfile template to Company | Kingdee | Project Team | 7-Nov-11 | 11-Nov-11 | ||||
| 2 | Prepare the related documents to Kingdee | ||||||||
| 2.1 | Data Preparation (standard) | ||||||||
| 2.1.1 | – COA and Currency | Company | Project Team | 15-Nov-11 | 22-Nov-11 | 3.00 | |||
| 2.1.2 | – Required Analyis Item List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
| 2.1.3 | – Customer and Vendor List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
| 2.1.4 | – Employee and Department List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
| 2.1.5 | – Unit of Measurement | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
| 2.1.6 | – Finished Goods and Raw Materials List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
| 3 | Hardware purchasing and Software Installation | ||||||||
| 3.1 | Install the hardware (for K/3 System) and Operation system, SQL Server | Company | IT | 7-Nov-11 | 18-Nov-11 | 1.00 | |||
| 3.2 | Confirm Hardware Readiness | Company | IT | 7-Nov-11 | 18-Nov-11 | ||||
| 3.3 | Confirm Software Box Set delivery | Company | Service | 7-Nov-11 | 18-Nov-11 | ||||
| 3.4 | Confirm environment Readiness(e.g DB, Window OS) | Company | IT | 7-Nov-11 | 18-Nov-11 | ||||
| 3.5 | Install the Database Server and MiddleWare Server | Kingdee | Service | 7-Nov-11 | 18-Nov-11 | ||||
| BLUEPRINT | |||||||||
| 4 | System Design | ||||||||
| 4.1 | Network & Database get ready (preferable) | KEE TAT LIGHTING LIMITED | IT | 7-Nov-11 | 18-Nov-11 | 1.00 | |||
| 4.2 | Business Study on Finance | Both | Project Team | 15-Nov-11 | 15-Nov-11 | ||||
| 4.3 | Initialization introduction | Both | Project Team | 15-Nov-11 | 15-Nov-11 | ||||
| 5 | Product Training | ||||||||
| 5.1 | Training to Key Users (HK) | 3.00 | |||||||
| 5.1.1 | Training on Master Setting and Initialization | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
| 5.1.2 | Training on Finance | ||||||||
| 5.1.2.1 | – General Ledger and Report Writer | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
| 5.1.2.2 | – Account Receivable and Payable, Fix Asset | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
| 5.1.3 | Administrator Training to IT Administrator | Kingdee | IT | 6-Dec-11 | 8-Dec-11 | ||||
| REALIZATION / EXECUTION | |||||||||
| 6 | System Initialization | ||||||||
| Financial Accounting implementation | |||||||||
| 6.1 | Prepare the Master file for import | Company | Project Team | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
| 6.2 | Create One Instance | Company | IT | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
| 6.3 | User authorization setting | Company | IT | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
| 6.4 | Config the Local Currency,COA and Voucher Group | Company | Accounting | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
| 6.5 | Basic Setting for Finance Module | Company | Project Team | 12-Dec-11 | 14-Dec-11 | ||||
| 6.6 | Import Master Data | Company | Project Team | 12-Dec-11 | 14-Dec-11 | 0.50 | |||
| Opening Balance Preparation | Company | ||||||||
| 6.7 | Input Opening Balance of December and Kingdee support | Company | Accounting | 12-Dec-11 | 14-Dec-11 | 5.00 | |||
| 6.8 | Input Outstanding ARAP Inovoice of December and Kingdee Support | Company | Accounting | 12-Dec-11 | 14-Dec-11 | ||||
| 6.9 | Check initial data December and close initialization with Kingdee Support | Company | Project Team | 12-Dec-11 | 14-Dec-11 | ||||
| 6.10 | Back-date transaction entry | Company | Project Team | 15-Dec-11 | 21-Dec-11 | ||||
| USER ACCEPTANCE TEST(UAT) | |||||||||
| 7 | Project Closure | Both | Project Team | 30-Dec-11 | 30-Dec-11 | ||||