The following is an example of implementation schedule for an ERP finance system. Total period requires 2 months at least :
SN | Phase / Task | Owner | Department Involved | Start Date | End Date | Est.Day | Status | Actual Date | |
PREPARATION | |||||||||
0 | Project Initiation | ||||||||
0.10 | Select Project Manager | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
0.20 | Prepare Project Kick-off Meeting | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
0.30 | Develop preliminary project scope and schedule | Kingdee | Management | 7-Nov-11 | 7-Nov-11 | ||||
1 | Kick Off Meeting | ||||||||
1.1 | Project Team Member List Arrangement | Both | Project Team | 7-Nov-11 | 11-Nov-11 | 0.50 | |||
1.2 | Prelimilary Understanding the Company Background, structure and others of Company | Kingdee | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
1.3 | Present the implementation workflow, ways and contents | Kingdee | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
1.4 | Define the implementation schedule | Both | Project Team | 7-Nov-11 | 7-Nov-11 | ||||
1.5 | Deliver the Masterfile template to Company | Kingdee | Project Team | 7-Nov-11 | 11-Nov-11 | ||||
2 | Prepare the related documents to Kingdee | ||||||||
2.1 | Data Preparation (standard) | ||||||||
2.1.1 | – COA and Currency | Company | Project Team | 15-Nov-11 | 22-Nov-11 | 3.00 | |||
2.1.2 | – Required Analyis Item List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
2.1.3 | – Customer and Vendor List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
2.1.4 | – Employee and Department List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
2.1.5 | – Unit of Measurement | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
2.1.6 | – Finished Goods and Raw Materials List | Company | Project Team | 15-Nov-11 | 22-Nov-11 | ||||
3 | Hardware purchasing and Software Installation | ||||||||
3.1 | Install the hardware (for K/3 System) and Operation system, SQL Server | Company | IT | 7-Nov-11 | 18-Nov-11 | 1.00 | |||
3.2 | Confirm Hardware Readiness | Company | IT | 7-Nov-11 | 18-Nov-11 | ||||
3.3 | Confirm Software Box Set delivery | Company | Service | 7-Nov-11 | 18-Nov-11 | ||||
3.4 | Confirm environment Readiness(e.g DB, Window OS) | Company | IT | 7-Nov-11 | 18-Nov-11 | ||||
3.5 | Install the Database Server and MiddleWare Server | Kingdee | Service | 7-Nov-11 | 18-Nov-11 | ||||
BLUEPRINT | |||||||||
4 | System Design | ||||||||
4.1 | Network & Database get ready (preferable) | KEE TAT LIGHTING LIMITED | IT | 7-Nov-11 | 18-Nov-11 | 1.00 | |||
4.2 | Business Study on Finance | Both | Project Team | 15-Nov-11 | 15-Nov-11 | ||||
4.3 | Initialization introduction | Both | Project Team | 15-Nov-11 | 15-Nov-11 | ||||
5 | Product Training | ||||||||
5.1 | Training to Key Users (HK) | 3.00 | |||||||
5.1.1 | Training on Master Setting and Initialization | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
5.1.2 | Training on Finance | ||||||||
5.1.2.1 | – General Ledger and Report Writer | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
5.1.2.2 | – Account Receivable and Payable, Fix Asset | Kingdee | Accounting | 6-Dec-11 | 8-Dec-11 | ||||
5.1.3 | Administrator Training to IT Administrator | Kingdee | IT | 6-Dec-11 | 8-Dec-11 | ||||
REALIZATION / EXECUTION | |||||||||
6 | System Initialization | ||||||||
Financial Accounting implementation | |||||||||
6.1 | Prepare the Master file for import | Company | Project Team | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
6.2 | Create One Instance | Company | IT | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
6.3 | User authorization setting | Company | IT | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
6.4 | Config the Local Currency,COA and Voucher Group | Company | Accounting | 12-Dec-11 | 14-Dec-11 | 1.00 | |||
6.5 | Basic Setting for Finance Module | Company | Project Team | 12-Dec-11 | 14-Dec-11 | ||||
6.6 | Import Master Data | Company | Project Team | 12-Dec-11 | 14-Dec-11 | 0.50 | |||
Opening Balance Preparation | Company | ||||||||
6.7 | Input Opening Balance of December and Kingdee support | Company | Accounting | 12-Dec-11 | 14-Dec-11 | 5.00 | |||
6.8 | Input Outstanding ARAP Inovoice of December and Kingdee Support | Company | Accounting | 12-Dec-11 | 14-Dec-11 | ||||
6.9 | Check initial data December and close initialization with Kingdee Support | Company | Project Team | 12-Dec-11 | 14-Dec-11 | ||||
6.10 | Back-date transaction entry | Company | Project Team | 15-Dec-11 | 21-Dec-11 | ||||
USER ACCEPTANCE TEST(UAT) | |||||||||
7 | Project Closure | Both | Project Team | 30-Dec-11 | 30-Dec-11 |