1.            Overview

The following specification is aimed for a WIP status report for HK factory but including those going to PRC factory for gluing and directly shipped from PRC.

wip-rpta

2.            Generation of Data

2.1         WIP Status per Work Center (16.20.24.19) – daily

wip-rptb

  • It gives the on hand qty of each work center at 0:00 that day.
  • Database fields are arranged in sequence of work center codes found in work center table.
  • Maximum array size is 130 work centers.
  • Any change to work center, add or delete, must be done after the report generation of that day.
  • This job must be done right after the system restart from backup.  No shopfloor feedback is allowed during the process.
  • Output Format:

“TP2” “3322 160 59231” 0 0 910 0 0 26606 7575 4559 0 32566 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

“tp2” “3322 161 00241” 0 0 0 0 0 0 0 0 0 2300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

“tp2” “3322 161 00521” 0 0 0 0 0 0 0 0 0 6760 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

2.2         Technical Stock on hand (16.20.24.18) – daily

wip-rptc

  • It gives the stock on hand of each technical stock location at 0:00 that day.
  • Data fields : pn, ts_location, current_onhand, xaction_qty_in_selected_date_range, calculated_onhand_at_start_time.
  • When Auto Date=Yes, selected date range will be today’s 0:00 to current time.
  • Output Format:

“ld_part” “ld_loc” “ld_qty_oh” 07/26/99 “02:17”

“3322 138 86621” “4cell” 68 0 68

“3322 160 52321” “4cell” 1 0 1

“3322 160 54591” “4subc” 339 0 339

“3322 160 55732” “4modu” 84 0 84

2.3       Week-To-Day Technical Stock Output (16.20.24.16) – daily

wip-rptd

  • It gives the week-to-day total output from technical stock locations.
  • When auto-date is set to yes, the selected date range will be from last Friday to current week Thursday.
  • Selected transaction and calculation method are as followings (4Cell as example) :
Loc Tr_type Address qty_change Qty to sum
4Cell ISS-TR 1main -500 500
4Cell ISS-TR 630 -1000 1000
1Main ISS-TR 4Cell -200 -200
630 ISS-TR 4Cell -100 -100
Total O/P: 1200
  • Output Format:

“pt_part” “tr_loc” “tr_qty_chg” 07/26/99

“3322 160 51481” “4SUBC” 1130

“3322 160 55191” “4SUBC” 2322

“3322 160 55281” “4SUBC” 711

“3322 160 55321” “4CELL” 7609

“3322 160 55331” “4CELL” 12911

2.4       Week-To-Day Work Center Output (16.20.24.17) – daily

wip-rpte

  • It gives the week-to-day output qty of work center 46 which is defined as the output of HK factory to PRC cutoff at 0:00 of that day.
  • When auto-date is set to yes, the selected date range will be from last Friday 0:00 to current week Thursday 24:00.
  • Output Format:

“tp2” “3322 160 59231” “LPA7569-1A BONDED CELL” “46” 3263

“tp2” “9360 276 30112” “LPH7764-1” “46” 10058

“TP2” “9360 277 30112” “LPH7555-3” “46” 13543

“tp3” “3322 160 54561” “LPH7408-3 GLUED CELL” “46” 1274

2.5       Yield Point Update (16.20.24.13) – weekly

wip-rptf

  • It gives a weekly update on the 5 pre-defined yield points based on lots closed in the past week.
  • Currently only defined for HK yield capturing only.  Additional yield points will be required for PRC operation.
  • Default yield should be updated manually for new project.
  • Output Format:

wip-rptg

2.6       Master Plan Upload (16.20.24.13) Weekly

wip-rpth

  • This function is built for direct upload from Excel spreadsheet on weekly basis, expected to be done on Friday noon time.
  • Excel format must follow the specification displayed on the screen.  Further, file must be saved in csv format.
  • The date stamp must be same as the one input on screen for validation purpose.

2.6       Master Plan Maintenance (16.20.24.5) – daily

wip-rpti

  • The maintenance of master plan is expected to be done off the Mfg/Pro and upload on weekly basis until full maintenance function is available.
  • Full master plan maintenance function include new master plan generation from prior data with back log consideration, frozen windows, security…etc.

3.     Report Printing and Definition

3.1       Selection Screen

wip-rptj

3.2       Field Definition for Form 2 (TP2/3)

  • Technology(Tech Grp) = product line from Item Master
  • Type Number = desc1 from item master
  • Major Account = design group from item master
  • Density (Den) = density from product parameter table
  • Yield Semi-finishing (Yld SF) = fab * fqc * bonding yield from product parameter table
  • Yeld Finishing (Yld Fin) = fab * fqc * bonding * fi * assy yield from product parameter table
  • Queued Qty in Work Center
  • S&B = wc 25 + 28 + 30
  • Filling = wc 35
  • FQC = wc 45
  • Bonding = wc 50
  • SF-TS = wc 46
  • Gluing = wc 47+ 55 + 56
  • FI = wc 58 + 60 + 61
  • Assy = wc 62 + 65 + 66 + 67
  • OQC = 80 + 94
  • Technical Stock = Total on hand qty of all technical stock locations
  • Forecast Output
  • Semi-Finishing (SF) =

Wc (25 + 28 + 30) * fab * fqc * bonding yield

+  Wc (35 + 45) * fqc * bonding yield

+  Wc (50) * bonding yield

  • Finishing (FIN) =

Semi-finishing O/P * fi * assy yield

+  Wc (46 + 47 + 55 + 56 + 58 + 60 + 61) * fi * assy yield

+  Wc (62 + 65 + 66 + 67) * assy yield

+  Wc (80+94) * 100% yield

  • Week-To-Day (W-T-D) WC46 O/P = total output qty of work center 46 from last Friday to current week Thursday.  It is considered as the output of HK Factory to PRC under production line TP3.
  • Week-To-Day (W-T-D) FIN O/P = total output qty of technical stock locations from last Friday to current week Thursday
  • Master Plan (HK) = Past Due, week n, week n+1 and week n+2 of master plan table ms_mstr.

wip-rptk